Difference between revisions of "CSIT/csit1810 plan"

From fd.io
Jump to: navigation, search
Line 23: Line 23:
 
|-
 
|-
 
| F0
 
| F0
| ..
+
| 2018-10-03
| Test cases code frozen. Only API adjustments, infra compatibility adjustments, bug fixes and low-risk changes accepted.
+
| Test case keywords code complete. Only low-risk changes accepted.
 
|-
 
|-
 
| RC1
 
| RC1
| ..
+
| 2018-10-10 (F0+7)
| Test code complete. Pull first release branch. Only bug fixes accepted in release branch. Date aligned with VPP RC1.
+
| Code complete. Pull first release branch. Only bug fixes accepted in release branch. Date aligned with VPP RC1.
 
|-
 
|-
 
| RC2
 
| RC2
| ..
+
| 2018-10-17 (RC1+7)
| Initial dry-run release tests of VPP RC2, performance and functional. Aligned with VPP RC2.
+
| Dry-run testing begins of VPP RC2, performance and functional. Date aligned with VPP RC2.
 
|-
 
|-
| Formal Release
+
| CSIT Release
| ..
+
| 2018-10-24 (RC2+7)
| CSIT code release complete. VPP release testing starts.
+
| CSIT release complete. VPP release testing starts. Date aligned with VPP Formal Release.
 
|-
 
|-
 
| Report Publish
 
| Report Publish
| ..
+
| 2018-11-07 (Rls+14)
 
| CSIT report published for VPP release.
 
| CSIT report published for VPP release.
 
|}
 
|}
  
 
== Expected Dependencies on Other Projects ==
 
== Expected Dependencies on Other Projects ==

Revision as of 17:33, 22 August 2018


Please be aware that this page is work-in-progress and more info is being added continuously.

Introduction

All CSIT release deliverables should be tracked in FDio CSIT Jira .using one of the following Jira Epic categories:

...

Release Deliverables

...

Release Milestones

Milestone Date Deliverables
F0 2018-10-03 Test case keywords code complete. Only low-risk changes accepted.
RC1 2018-10-10 (F0+7) Code complete. Pull first release branch. Only bug fixes accepted in release branch. Date aligned with VPP RC1.
RC2 2018-10-17 (RC1+7) Dry-run testing begins of VPP RC2, performance and functional. Date aligned with VPP RC2.
CSIT Release 2018-10-24 (RC2+7) CSIT release complete. VPP release testing starts. Date aligned with VPP Formal Release.
Report Publish 2018-11-07 (Rls+14) CSIT report published for VPP release.

Expected Dependencies on Other Projects