CSIT/csit1810 plan
From fd.io
Please be aware that this page is work-in-progress and more info is being added continuously.
Contents
Introduction
All CSIT release deliverables should be tracked in FDio CSIT Jira .using one of the following Jira Epic categories:
...
Release Deliverables
...
Release Milestones
Milestone | Date | Deliverables |
---|---|---|
F0 | 2018-10-03 | Test case keywords code complete. Only low-risk changes accepted. |
RC1 | 2018-10-10 (F0+7) | Code complete. Pull first release branch. Only bug fixes accepted in release branch. Date aligned with VPP RC1. |
RC2 | 2018-10-17 (RC1+7) | Dry-run testing begins of VPP RC2, performance and functional. Date aligned with VPP RC2. |
CSIT Release | 2018-10-24 (RC2+7) | CSIT release complete. VPP release testing starts. Date aligned with VPP Formal Release. |
Report Publish | 2018-11-07 (Rls+14) | CSIT report published for VPP release. |