Difference between revisions of "CSIT/csit1810 plan"

From fd.io
Jump to: navigation, search
(Created page with "Category:Release Plan '''<span style="color: red">Please be aware that this page is work-in-progress and more info is being added continuously.</span>''' == Introduction...")
 
Line 18: Line 18:
  
 
{| class="wikitable"
 
{| class="wikitable"
! CSIT-18.10 Milestone
+
! Milestone
 
! Date
 
! Date
 
! Deliverables
 
! Deliverables
 
|-
 
|-
| Code complete
+
| F0
 
| ..
 
| ..
| Test cases code frozen. Only bug fixes and low-risk changes accepted. Aligned with VPP RC2.
+
| Test cases code frozen. Only API adjustments, infra compatibility adjustments, bug fixes and low-risk changes accepted.
 
|-
 
|-
| Branch pull
+
| RC1
 
| ..
 
| ..
| Pull CSIT-18.10 throttle branch. Aligned with VPP RC2. Initial VPP RC2 performance tests.
+
| Test code complete. Pull first release branch. Only bug fixes accepted in release branch. Date aligned with VPP RC1.
 
|-
 
|-
| CSIT Release
+
| RC2
 
| ..
 
| ..
| CSIT-18.10 test code complete. VPP 18.07 rls testing.
+
| Initial dry-run release tests of VPP RC2, performance and functional. Aligned with VPP RC2.
 
|-
 
|-
| CSIT Report
+
| Formal Release
 
| ..
 
| ..
| CSIT-18.10 report to be published.
+
| CSIT code release complete. VPP release testing starts.
 +
|-
 +
| Report Publish
 +
| ..
 +
| CSIT report published for VPP release.
 
|}
 
|}
  
 
== Expected Dependencies on Other Projects ==
 
== Expected Dependencies on Other Projects ==

Revision as of 16:47, 22 August 2018


Please be aware that this page is work-in-progress and more info is being added continuously.

Introduction

All CSIT release deliverables should be tracked in FDio CSIT Jira .using one of the following Jira Epic categories:

...

Release Deliverables

...

Release Milestones

Milestone Date Deliverables
F0 .. Test cases code frozen. Only API adjustments, infra compatibility adjustments, bug fixes and low-risk changes accepted.
RC1 .. Test code complete. Pull first release branch. Only bug fixes accepted in release branch. Date aligned with VPP RC1.
RC2 .. Initial dry-run release tests of VPP RC2, performance and functional. Aligned with VPP RC2.
Formal Release .. CSIT code release complete. VPP release testing starts.
Report Publish .. CSIT report published for VPP release.

Expected Dependencies on Other Projects