Difference between revisions of "VPP/CommitterTasks/FinalReleaseCandidate"

From fd.io
< VPP
Jump to: navigation, search
(Created page with "== VPP RC2 Milestone Tasklist == # At least one week prior to RC2 Milestone, send an email reminder to vpp-dev@lists.fd.io. See example [https://lists.fd.io/pipermail/vpp-dev...")
 
(VPP RC2 Milestone Tasklist)
Line 1: Line 1:
 
== VPP RC2 Milestone Tasklist ==
 
== VPP RC2 Milestone Tasklist ==
  
# At least one week prior to RC2 Milestone, send an email reminder to vpp-dev@lists.fd.io. See example [https://lists.fd.io/pipermail/vpp-dev/2018-January/007782.html email].
+
1. At least one week prior to RC2 Milestone, send an email reminder to vpp-dev@lists.fd.io. See example [https://lists.fd.io/pipermail/vpp-dev/2018-January/007814.html email].
 +
 
 +
2. Resend the reminder a day or two before RC2.
 +
 
 +
3. [https://wiki.fd.io/view/VPP/Pushing_and_Testing_a_Tag Lay down a tag] (v18.01-rc2) on stable/1801 at HEAD.
 +
 
 +
4. Send an email to vpp-dev@lists.fd.io and csit-dev@lists.fdio announcing the completion of RC2.  See example [https://lists.fd.io/pipermail/vpp-dev/2018-January/007863.html email].
 +
:NOTE: The CSIT code freeze date typically co-incides with RC2.  At this point, they will pull their release throttle branch (e.g. rls1801) and add appropriate jenkins jobs (much like the VPP RC1 branch pull).
 +
 
 +
5. Keep an eye on the release throttle gerrit queue for a patch to start using the CSIT release branch.  Merge it when it has been verified.
 +
:Examples:
 +
::[https://gerrit.fd.io/r/#/q/project:vpp+AND+branch:stable/1801 VPP stable/1801 Gerrit Filter]
 +
::VPP patch to use CSIT Release branch: https://gerrit.fd.io/r/#/c/10071/
 +
 
 +
6. Continue to watch/merge patches in the VPP release throttle branch.

Revision as of 18:30, 5 February 2018

VPP RC2 Milestone Tasklist

1. At least one week prior to RC2 Milestone, send an email reminder to vpp-dev@lists.fd.io. See example email.

2. Resend the reminder a day or two before RC2.

3. Lay down a tag (v18.01-rc2) on stable/1801 at HEAD.

4. Send an email to vpp-dev@lists.fd.io and csit-dev@lists.fdio announcing the completion of RC2. See example email.

NOTE: The CSIT code freeze date typically co-incides with RC2. At this point, they will pull their release throttle branch (e.g. rls1801) and add appropriate jenkins jobs (much like the VPP RC1 branch pull).

5. Keep an eye on the release throttle gerrit queue for a patch to start using the CSIT release branch. Merge it when it has been verified.

Examples:
VPP stable/1801 Gerrit Filter
VPP patch to use CSIT Release branch: https://gerrit.fd.io/r/#/c/10071/

6. Continue to watch/merge patches in the VPP release throttle branch.