Difference between revisions of "CSIT/csit1810 plan"

From fd.io
Jump to: navigation, search
Line 28: Line 28:
 
| RC1
 
| RC1
 
| 2018-10-10 (F0+7)
 
| 2018-10-10 (F0+7)
| Code complete. Pull first release branch. Only bug fixes accepted in release branch. Date aligned with VPP RC1.
+
| Code complete. Pull first release branch. Only bug fixes accepted in release branch. Date aligned with [https://wiki.fd.io/view/Projects/vpp/Release_Plans/Release_Plan_18.10#Release_Milestones VPP RC1].
 
|-
 
|-
 
| RC2
 
| RC2
 
| 2018-10-17 (RC1+7)
 
| 2018-10-17 (RC1+7)
| Dry-run testing begins of VPP RC2, performance and functional. Date aligned with VPP RC2.
+
| Dry-run testing begins of VPP RC2, performance and functional. Date aligned with [https://wiki.fd.io/view/Projects/vpp/Release_Plans/Release_Plan_18.10#Release_Milestones VPP RC2].
 
|-
 
|-
 
| CSIT Release
 
| CSIT Release
 
| 2018-10-24 (RC2+7)
 
| 2018-10-24 (RC2+7)
| CSIT release complete. VPP release testing starts. Date aligned with VPP Formal Release.
+
| CSIT release complete. VPP release testing starts. Date aligned with [https://wiki.fd.io/view/Projects/vpp/Release_Plans/Release_Plan_18.10#Release_Milestones VPP Formal Release].
 
|-
 
|-
 
| Report Publish
 
| Report Publish

Revision as of 17:40, 22 August 2018


Please be aware that this page is work-in-progress and more info is being added continuously.

Introduction

All CSIT release deliverables should be tracked in FDio CSIT Jira .using one of the following Jira Epic categories:

...

Release Deliverables

...

Release Milestones

Milestone Date Deliverables
F0 2018-10-03 Test case keywords code complete. Only low-risk changes accepted.
RC1 2018-10-10 (F0+7) Code complete. Pull first release branch. Only bug fixes accepted in release branch. Date aligned with VPP RC1.
RC2 2018-10-17 (RC1+7) Dry-run testing begins of VPP RC2, performance and functional. Date aligned with VPP RC2.
CSIT Release 2018-10-24 (RC2+7) CSIT release complete. VPP release testing starts. Date aligned with VPP Formal Release.
Report Publish 2018-11-07 (Rls+14) CSIT report published for VPP release.

Expected Dependencies on Other Projects