CSIT/csit1810 plan

From fd.io
< CSIT
Revision as of 17:40, 22 August 2018 by Mackonstan (Talk | contribs)

Jump to: navigation, search


Please be aware that this page is work-in-progress and more info is being added continuously.

Introduction

All CSIT release deliverables should be tracked in FDio CSIT Jira .using one of the following Jira Epic categories:

...

Release Deliverables

...

Release Milestones

Milestone Date Deliverables
F0 2018-10-03 Test case keywords code complete. Only low-risk changes accepted.
RC1 2018-10-10 (F0+7) Code complete. Pull first release branch. Only bug fixes accepted in release branch. Date aligned with VPP RC1.
RC2 2018-10-17 (RC1+7) Dry-run testing begins of VPP RC2, performance and functional. Date aligned with VPP RC2.
CSIT Release 2018-10-24 (RC2+7) CSIT release complete. VPP release testing starts. Date aligned with VPP Formal Release.
Report Publish 2018-11-07 (Rls+14) CSIT report published for VPP release.

Expected Dependencies on Other Projects