Introduction
This page tracks release information for 20.01
Release Deliverables
| Name | Description | Status | 
|---|---|---|
| Restconf | Restconf implementation | In-progress | 
| Migrate into Netopeer2 Project | In-progress | |
| NAT | NAT YANG Model | In-progress | 
| FIB | FIB YANG Model | 
Release Milestones
The schedule below is DRAFT
the milestones' time will be at 18:00 UTC on the day of the milestone.
| Milestone | Date | Deliverables | 
|---|---|---|
| F0 | 2020-01-07 | APIs frozen. Only low-risk changes accepted on main branch. | 
| RC1 | 2020-01-14 (F0 + 7) | Code complete, pull first release throttle branch, only bug fixes accepted on throttle train. After pull: main branch reopens for new feature / risky commits. First artifacts posted. | 
| RC2 | 2020-01-21 (RC1 + 7) | Second artifacts posted. | 
| Formal Release | 2020-01-28 (RC2 + 7) | 20.01 release artifacts available | 
NOTE: Dates chosen based on:
- end-month release
- milestone + days
- release date after VPP community meeting, for discussion, go/no-go
Once we've pulled the 20.01 release throttle
We need to be disciplined with respect to bugfix commits. Here are a few common-sense suggestions:
-  All bug fixes must be double-committed to the release throttle as well as to the master branch
- Commit first to the release throttle, then "git cherry-pick" into master
- Manual merges may be required, depending on the degree of divergence between throttle and master
 
-  All bug fixes need to have a Jira ticket 
- Please put Jira IDs into the commit messages.
- Please use the same Jira ID for commits into the stable branch and master.
 